IRR, NPV and real value creation: assessing profitability properly

Analysis 19 November, 2026

Visualisation of a stackable large-scale battery storage next to a town

IRR, NPV and real value creation: assessing profitability properly

The internal rate of return (IRR) is often treated in the market as the key metric for storage investments. As a basis for comparison, however, it is unsuitable: it measures a percentage return, not the value actually created over the entire project life.

When comparing lithium-ion and zinc-based systems, this leads to systematic misinterpretation:

  • Lithium systems show higher IRRs on paper because of their shorter lifetimes.
  • Zinc-based systems are designed for much longer operating lives and deliver stable cash flows over decades.
  • The IRR favours early returns and penalises long-term value creation.
  • Where lifetimes differ, IRR comparisons are methodologically invalid.
  • Only the net present value (NPV) reflects the enterprise value actually created.

In short

A sound NPV comparison shows that over the project life, long-lived zinc-based systems create clearly more value.

Why the IRR is unsuitable as a yardstick

The IRR measures the return on the capital employed, not the absolute value a project adds. Its assumptions lead to systematic distortions in long-life infrastructure projects:

  • It assumes that all interim surpluses are reinvested at the IRR itself. In practice this is unrealistic, especially for high IRRs.
  • It implicitly assumes that follow-on and supplementary investments earn the same IRR. This hardly ever happens in real capital markets either.
  • Projects with shorter lifetimes are favoured, because early cash flows carry more weight in the calculation.
  • Long-term, stable payment streams are structurally undervalued.
  • It ignores the absolute amount of value created and says nothing about the actual contribution to enterprise value.

The comparison of lithium and zinc-based systems makes this distortion visible: lithium storage with a shorter technical life often shows higher IRRs, while long-lived zinc-based systems create more value over the full project life.

Why only the net present value (NPV) matters for decisions

The NPV measures the actual increase in value in euros, under realistic reinvestment assumptions (e.g. at the WACC). It answers the central question: how much additional enterprise value is created over the entire project life? Compared with the IRR, this has several advantages:

  • Realistic reinvestment assumption at the market rate instead of the project-specific IRR
  • Fair comparison of projects with different lifetimes
  • Reliable valuation even where investment sizes differ
  • Consistent representation of the entire project life
  • Direct measurement of the absolute contribution to enterprise value

Chain investment as a fair comparison

For a sound comparison, the shorter-lived project is extended in the model:

  • The lithium project is repeated until the total life of the zinc-based system is reached.
  • Market, cost and technology assumptions are carried forward realistically.
  • Both alternatives are assessed over equally long periods.
  • The NPV is calculated consistently across the whole comparison period.
  • The comparison is based on the cumulative NPV, and therefore on the value created.

Conclusion

  • The NPV comparison is the decisive valuation method for multi-hour battery storage projects.
  • IRR-based comparisons can systematically distort investment decisions where project lifetimes differ.
  • Over a comparable period, long-lived zinc-based systems generate the higher NPV and therefore the greater contribution to enterprise value.

Contact Us

Discuss Your Project

Battery storage systems are long-term infrastructure investments. Their success depends on how well technology, system design, safety and economics work together.

In an initial consultation, we clarify:

  • Optimal storage duration and sizing
  • Technical and regulatory requirements
  • Economics and revenue potential
  • Suitable project and delivery structure

You get a sound basis for your investment decision and the next steps of your project.